Wentworth is proud to have supported the Allerdene Bridge project by delivering innovative and challenging temporary work solutions. A truly rewarding achievement.

Wentworth provided the below services:

  • Developed the demolition sequence design and drawings, assessing the partial structure under demolition loading.
  • Prepared CAD drawings of the existing bridge structure, traced from historic drawings.
  • Acted as Contractor's Responsible Engineer for Design (CRE-D) in the Network Rail approval process.
    Visually searched image write a short alt image text description for this picture for a website reader An image showing the back and side profile of two construction workers wearing white hard hats and neon yellow high-visibility vests over dark jackets.
    Visually searched image write a short alt image text description for this picture for a website reader An image showing the back and side profile of two construction workers wearing white hard hats and neon yellow high-visibility vests over dark jackets.