1 Victoria Street, London
1 Victoria Street, London
Client: Keltbray (Demolition Contractor)
Developer: Stanhope and Mitsubishi Estate London (Joint Venture)
Project: 1 Victoria Street - Sustainable Commercial Office Redevelopment
Location: Westminster, London
Architect: Allford Hall Monaghan Morris (AHMM)
Structural engineer: Heyne Tillett Steel
Stanhope and Mitsubishi Estate London are replacing a 1965 office building with a new 10-storey post-tensioned concrete frame on a 7,400m² footprint in the heart of Westminster. The existing structure (nine storeys above ground with two basement levels) required complete demolition down to B2 level before construction of the new sustainable commercial offices could begin. Wentworth provided construction engineering from initial structural investigation through demolition completion including designing temporary works and design support during the construction of the new structure. This support enabled Keltbray to maintain high momentum while managing risks in this geotechnically sensitive heritage location.
10
Storey new post-tensioned concrete frame
100+
Elements GPR scanned
7,400m²
Existing building footprint
OUR ROLE
OUR ROLEWentworth's engagement began with a comprehensive pre-demolition structural investigation, scanning over 100 structural elements using Ground Penetrating Radar (GPR) to map reinforcement and concrete cover. We designed and implemented hydraulic load tests on floor slabs to verify capacity for heavy demolition plant. During demolition, we provided agile temporary works designs, including basement retention analysis and early piling solutions. Our work combined archive drawing studies, 3D geotechnical ground modelling, and utility damage assessments and structural finite element analysis to optimise the demolition sequence and enable early foundation works for the new structure.
We are now designing the temporary works during the construction phase of the new building by undertaking extensive structural modelling to assess the stability of the 2No cores in the temporary condition, and design the steel grillages for the tower cranes that will be installed on top.
We are now designing the temporary works during the construction phase of the new building by undertaking extensive structural modelling to assess the stability of the 2No cores in the temporary condition, and design the steel grillages for the tower cranes that will be installed on top.
Capabilities
Capabilities- Buildings
- Demolition
- Structural Investigation and Testing
Proving floor capacity for demolition
Proving floor capacity for demolitionBefore Keltbray could bring heavyweight 13te excavators and bobcats onto the existing floors to start the demolition works, we had to verify that the 1965-era concrete floor slabs could safely support the heavy loads. The building's age and limited original documentation meant that the slab capacities were uncertain, adding significant risk for both the demolition programme and overall site safety.
Wentworth’s in-house site and investigations team designed and implemented hydraulic load test systems, applying controlled loads to selected slabs while recording deflection and monitoring slab condition throughout testing.
Our GPR scanning of over 100 structural elements provided reinforcement geometry and concrete cover data, which we correlated with breakout surveys and core samples to build a complete structural picture. This combination of non-destructive testing and targeted intrusive investigation confirmed realistic load capacities without extensive breakouts.
The verified slab capacities gave Keltbray certainty to mobilise its demolition plant, enabling an efficient top-down demolition sequence across the nine-storey structure.
Wentworth’s in-house site and investigations team designed and implemented hydraulic load test systems, applying controlled loads to selected slabs while recording deflection and monitoring slab condition throughout testing.
Our GPR scanning of over 100 structural elements provided reinforcement geometry and concrete cover data, which we correlated with breakout surveys and core samples to build a complete structural picture. This combination of non-destructive testing and targeted intrusive investigation confirmed realistic load capacities without extensive breakouts.
The verified slab capacities gave Keltbray certainty to mobilise its demolition plant, enabling an efficient top-down demolition sequence across the nine-storey structure.
Designing unrestricted basement access
Designing unrestricted basement accessThe 7,400m² footprint included two basement levels that would eventually accommodate new foundations, but temporary propping of the retaining walls during demolition would impede access. Traditional temporary works approaches would have filled the basement with propping, limiting plant movement until the upper levels are removed and creating congestion.
We conducted detailed studies of archive drawings, developed 3D geotechnical ground models, and carried out utility damage assessments to understand the existing retaining wall construction and surrounding ground conditions. Through finite element analysis of the walls and soil-structure interaction plus movement analysis for utility damage assessments, we demonstrated that the existing retaining walls could safely cantilever without temporary support throughout the demolition phase.
This unrestricted basement access increased both safety and efficiency of the construction works, enabling Keltbray to complete demolition down to B2 level across the full footprint without the constraints of internal propping.
We conducted detailed studies of archive drawings, developed 3D geotechnical ground models, and carried out utility damage assessments to understand the existing retaining wall construction and surrounding ground conditions. Through finite element analysis of the walls and soil-structure interaction plus movement analysis for utility damage assessments, we demonstrated that the existing retaining walls could safely cantilever without temporary support throughout the demolition phase.
This unrestricted basement access increased both safety and efficiency of the construction works, enabling Keltbray to complete demolition down to B2 level across the full footprint without the constraints of internal propping.
Enabling early piling around existing core structure
Enabling early piling around existing core structureTo protect the programme, Keltbray wanted to start the piling works for the new 10-storey post-tensioned concrete frame before the full demolition was complete. However, the existing concrete cores were still in place and providing lateral stability to the building, making early pile installation around them highly complex and a risk.
To mitigate this risk, Wentworth developed a streamlined, minimally invasive engineering solution involving partial slab removal and notch openings in the core walls. This approach was carefully coordinated with the demolition programme to manage evolving load conditions as the structure came down. Rather than extensive propping, our final design relied on minimal proprietary propping, selected specifically to accommodate pile rig access and movements.
Due to this solution, Keltbray was able to work simultaneously on both demolition and piling operations optimising the programme speed.
To mitigate this risk, Wentworth developed a streamlined, minimally invasive engineering solution involving partial slab removal and notch openings in the core walls. This approach was carefully coordinated with the demolition programme to manage evolving load conditions as the structure came down. Rather than extensive propping, our final design relied on minimal proprietary propping, selected specifically to accommodate pile rig access and movements.
Due to this solution, Keltbray was able to work simultaneously on both demolition and piling operations optimising the programme speed.
Migrating Corrosion Inhibitor (MCI) concrete application
Migrating Corrosion Inhibitor (MCI) concrete applicationWe selected various concrete elements for a trial application of an MCI product. When applied in a liquid form, the MCI penetrates cementitious materials, forming a protective layer on embedded reinforcing. Wentworth applied the product and monitored corrosion rates over a six-month period. This type of system can potentially extend the lifespan of structural elements by 15+ years.
Outcomes
OutcomesThis project demonstrates how early involvement of our technical engineers, combined with our in-house site investigations and testing team, enabled us to validate solutions in real time against existing structural capacity. By solving the key technical challenges prior to coming to site, we enabled Keltbray to execute a complex Westminster demolition with confidence and efficiency.
Key results:
The project is on track for completion in 2028.
Key results:
- Contractor confidence: Verified floor capacities through hydraulic load testing enabled safe deployment of heavy demolition plant across nine storeys
- Unrestricted basement access: Cantilevered retaining walls eliminated the need for internal propping, increasing safety and efficiency across a 7,400m² footprint
- Programme protection: Early piling solution enabled simultaneous demolition and foundation works around existing cores
- Minimal intrusive work: GPR scanning of 100+ elements combined with targeted breakouts provided comprehensive structural data without large-scale breakouts
- Agile delivery: Responsive temporary works designs maintained high momentum throughout the fast-paced demolition phase
- Innovation testing: MCI application trials demonstrated potential to extend the structural lifespan by 15+ years.
- Heritage location sensitivity: 3D geotechnical modelling and damage assessments to protect the adjacent Westminster Abbey and Palace of Westminster buildings.
The project is on track for completion in 2028.